Very steep slope · Dangerous

12/12 Roof Pitch

A 12/12 roof rises 12 inches for every 12 inches of horizontal run. That is a 45.00° angle, a grade of 100.0% and a roof area multiplier of 1.414, so every square foot of plan area becomes 1.414 square feet of roof surface.

45.00°run 12rise 12
Angle45.00°
Slope100.0%
Area multiplier1.414
Rise per metre1,000 mm
Rafter per ft of run16.97 in
Hip/valley per ft of run20.78 in

Rafter length for a 12/12 pitch

Multiply the horizontal run by 1.414. Every foot of run needs 16.97 inches of common rafter. Add the overhang (horizontal overhang × 1.414) and deduct half the ridge board thickness.

Building spanRun (½ span)Common rafterRidge rise
12 ft6 ft8 ft 5¾ in6 ft 0 in
16 ft8 ft11 ft 3¾ in8 ft 0 in
20 ft10 ft14 ft 1¾ in10 ft 0 in
24 ft12 ft16 ft 11¾ in12 ft 0 in
28 ft14 ft19 ft 9½ in14 ft 0 in
32 ft16 ft22 ft 7½ in16 ft 0 in
36 ft18 ft25 ft 5½ in18 ft 0 in
40 ft20 ft28 ft 3½ in20 ft 0 in

Gable roof, imperial. Rafter length is measured along the slope from wall plate to ridge centre line, before eave overhang and ridge board deduction.

Building spanRun (½ span)Common rafterRidge rise
4 m2 m2.83 m2.00 m
6 m3 m4.24 m3.00 m
8 m4 m5.66 m4.00 m
10 m5 m7.07 m5.00 m
12 m6 m8.49 m6.00 m

Gable roof, metric. Rafter length is measured along the slope from wall plate to ridge centre line, before eave overhang and ridge board deduction.

Roof area at 12/12

Roof surface area = plan area × 1.414. Use the roof calculator for multi-section roofs, waste and material costs.

Plan areaRoof surfaceSquares (+10%)Shingle bundles
1,000 sq ft1,414 sq ft15.647
1,500 sq ft2,121 sq ft23.371
2,000 sq ft2,828 sq ft31.194
2,500 sq ft3,536 sq ft38.9117
3,000 sq ft4,243 sq ft46.7141

Plan area includes eave overhangs. Bundles assume 3 bundles per square (100 sq ft) with 10% waste; hips, valleys and dormers need more.

Plan areaRoof surfaceWith 10% waste
80 m²113.1 m²124.5 m²
100 m²141.4 m²155.6 m²
150 m²212.1 m²233.3 m²
200 m²282.8 m²311.1 m²
250 m²353.6 m²388.9 m²

Plan area is the footprint measured to the outside of the eaves. Multiply by 1.414 for the sloped surface.

Roofing materials for a 12/12 pitch (US & Canada)

Minimum slopes from the 2021 International Residential Code. Canadian codes and manufacturers use similar limits for shingles and metal. Minimum pitch by material →

Roofing systemAt this pitchCode section
Asphalt shinglesMeets the 2/12 minimumIRC R905.2.2
Clay & concrete tileMeets the 2½/12 minimumIRC R905.3.2
Metal roof shinglesMeets the 3/12 minimumIRC R905.4.2
Slate & slate-type shinglesMeets the 4/12 minimumIRC R905.6.2
Wood shingles & shakesMeets the 3/12 minimumIRC R905.7.2 / R905.8.2
Standing-seam metal panelsMeets the ¼/12 minimumIRC R905.10.2
Lapped (exposed-fastener) metal panelsMeets the ½/12 minimumIRC R905.10.2
Mineral-surfaced roll roofingMeets the 1/12 minimumIRC R905.5.2
Membranes (TPO, EPDM, modified bitumen, built-up)Allowed, but normally used on low-slope roofsIRC R905.9–R905.13

Roofing materials for a 12/12 pitch (Australia & UK)

Typical manufacturer minimums. Check the specific product, sheet thickness, rafter length and exposure before ordering.

Roofing systemAt this pitchNotes
Concealed-fix steel deck (e.g. Lysaght Klip-Lok 700)Meets the typical 1° minimum1° applies to thicker sheet; 0.42 BMT is generally 2°.
Trapezoidal steel sheet (e.g. Lysaght Trimdek)Meets the typical 2° minimum—
Corrugated steel sheet (e.g. Lysaght Custom Orb)Meets the typical 5° minimum—
Interlocking concrete or terracotta tilesMeets the typical 15° minimumProfile dependent; many UK interlocking tiles need 17.5°–22.5°.
Natural slateMeets the typical 20° minimumTypical for larger slates; smaller slates and exposed sites need steeper pitches.
Plain tiles (clay or concrete)Meets the typical 35° minimumSome products allow 30°.
Flat-roof membranes (EPDM, single-ply, felt)Usually reserved for flat and low-slope roofsDesigned for a finished fall of about 1:80 (0.7°) or more.

Is a 12/12 roof steep?

Very steep roofs are mostly architectural: A-frames, Gothic and Tudor styles, and dormers. Expect a steep-slope labour surcharge on every quote.

A 12/12 roof cannot be walked. All work needs roof jacks or staging plus a personal fall arrest system.

12/12 roof pitch FAQ

What is a 12/12 roof pitch in degrees?

A 12/12 pitch is 45.00°. It rises 12 inches per 12 inches of run, so the angle is arctan(12 ÷ 12). As a percentage that is a slope of 100.0%, and in metric it rises 1,000 mm per metre.

What is the roof pitch multiplier for 12/12?

The 12/12 multiplier is 1.414. Multiply the roof's plan (footprint) area by 1.414 to get the sloped surface area. A 2,000 sq ft plan area, for example, is 2,828 sq ft of roof before waste.

How do I calculate rafter length for a 12/12 pitch?

Multiply the horizontal run by 1.414. Each foot of run needs 16.97 inches of rafter, so a 24 ft wide gable (12 ft run) needs a common rafter of about 16 ft 11¾ in before adding the overhang and deducting half the ridge board. Hip and valley rafters on a regular hip roof need 20.78 inches per foot of common run.

Can you walk on a 12/12 roof?

A 12/12 roof cannot be walked. All work needs roof jacks or staging plus a personal fall arrest system. OSHA (29 CFR 1926.500) treats any roof steeper than 4/12 as a steep roof for fall protection purposes.

What roofing materials can go on a 12/12 pitch?

Under the US International Residential Code a 12/12 pitch meets the minimum slope for asphalt shingles, clay & concrete tile, metal roof shingles, slate & slate-type shingles, wood shingles & shakes, standing-seam metal panels, lapped (exposed-fastener) metal panels and mineral-surfaced roll roofing. Always check the manufacturer's installation instructions and your local code.